Designed as post-column, the bridge uses 13x3 post-columns of Ø120 cm and is of length 12x25.00 m. (300 m). Within the context of the project, 600 m posts, 8.500 m³ concrete, 170.000 m³ excavation and fill, 18.500 m³ fortification, production of 12x6 items of pre-stressed beams were done and the bridge went into operation.
Client: General Directorate of State Highways
Start Date: 11.08.2000
End Date: 30.11.2003