EIB-R-03 Merzifon – Çorum Road (Section I)
Financed by EIB and Republic of Turkey, project is 26.700 m 2 x 2 divided road. Within the project 4 at grade junctions, 2 bridged junctions, 1 bridge, and 1.600.000 m³ excavation, 1.400.000 m³ backfilling, 650 tons of reinforcement, 30.000 m³ concrete, 355.000 tons of plant xix sub-foundation, 380.000 tons of plant mix foundation, 500.000 m² bituminous foundation, 650.000 m² binder, 650.000 m² asphalt surface coating will be done.
Client: General Directorate of State Highways
Start Date: 22.03.2005
End Date: 19.10.2011