EIB-R-04 Merzifon - Çorum Road ( Section II)
Financed by EIB and Republic of Turkey, project is 29.600 m, 2 x 2 divided road. Within the project 7 at grade junctions, 1 bridged junction, 1 bridge, and 1.640.000 m³ excavation, 1.525.000 m³ backfilling, 425 tons of reinforcement, 18.900 m³ concrete, 400.000 tons of plant mix sub-foundation, 410.000 tons of plant mix foundation, 500.000 m² bituminous foundation, 650.000 m² binder, 650.000 m² asphalt surface coating have been executed.
Client: General Directorate of State Highways
Start Date: 22.03.2005
End Date: 31.12.2011